Construction of a PSZOK in Glogow

Construction of a PSZOK in Glogow

Location
Implementation date:
08.2017
-
12
.
2018
Scope of work:
RIPOK MBP/ construction of PSZOK on the premises of the Waste Neutralization Plant in Glogow, 3 Komunalna Street.
Installation capacity:

Description of implementation

Range:‍

  1. Social building
  2. Reconstruction of the social part of the existing building
  3. Waste boxes
  4. Monolithic and prefabricated retaining walls
  5. Water and sewage networks and installations
  6. Land development
  7. Road surfaces
  8. Electrical works

‍Investor: GPK-SUEZ Glogow Ltd.

Realization Gallery

No items found.
The entrusted work was carried out on time, in a professional manner and with due diligence according to our requirements.
Zbigniew Rybka
CEO
See other testimonials

See also

Construction and equipment of a mixed municipal waste sorting plant with a composting plant and a solid alternative fuel production facility and accompanying infrastructure in Balin

Balin
Implementation date:
10.2014
-
05
.
2015
See implementation
General contracting

Construction of a sorting hall, accompanying infrastructure, educational path, and reconstruction and expansion of the existing yard for construction waste in Chojnice

Chojnice
Implementation date:
07.2022
-
11
.
2023
See implementation
General contracting

Design, modernization and expansion of the existing sewage sludge composting plant at Świderska Street in Lukow

Arc
Implementation date:
07.2021
-
01
.
2023
See implementation
Design and consulting
General contracting
Technologies