Expansion of the Recovery and Neutralisation Plant in Katowice - expansion of the mechanical part of the installation for preparation of waste for biological processing and production of alternative fuel

Expansion of the Recovery and Neutralisation Plant in Katowice - expansion of the mechanical part of the installation for preparation of waste for biological processing and production of alternative fuel

Location
Implementation date:
10.2016
-
12
.
2017
Scope of work:
Expansion of the Recovery and Disposal Plant in Katowice - expansion of the mechanical part of the plant for preparing waste for biological processing and for producing alternative fuel.
Installation capacity:
50000

Description of implementation

The purpose of the investment is to expand the Recovery and Disposal Plant in Katowice - to expand the mechanical part of the plant for preparing waste for biological processing and for producing alternative fuel.

The scope of work included:

  • preparation of project documentation
  • detailed designs
  • reconstruction and renovation of the existing composting hall and waste reception hall, together with dismantling of the existing installations and technological equipment inside the hall and their parts protruding outside the hall
  • Delivery, installation and commissioning at the above-mentioned facilities of a new installation / process line for mechanical preparation of waste for biological processing and for the production of alternative fuel with a capacity for a stream of mixed municipal waste with a bulk density of min. 350 kg/m3 min. 50,000 t/year with single-shift operation
  • Construction of supporting infrastructure.

Realization Gallery

No items found.
The entrusted work was carried out on time, in a professional manner and with due diligence according to our requirements.
Robert Potucha
Vice President
See other testimonials

See also

Design and construction of a digestion plant and a shed and storage boxes at the "Eagle Pond" ZUOK

Ceków
Implementation date:
11.2020
-
05
.
2023
See implementation
Design and consulting
General contracting

Design, modernization and expansion of the existing sewage sludge composting plant at Świderska Street in Lukow

Arc
Implementation date:
07.2021
-
01
.
2023
See implementation
Design and consulting
General contracting

Expansion of the biological part of the mixed municipal waste processing installation located at the landfill site in Ruda near/Wielun.

Wieluń
Implementation date:
02.2013
-
07
.
2013
See implementation
Design and consulting